Amendment to Award of Contract for the Provision of Multi-Disciplinary Design Team Services for the Vine Project in Central Library, Peterborough - MAY24/CMDN/112

With approval from the Monitoring Officer and the Growth, Resources and Communities Scrutiny Committee Chair, the urgency provisions to waive the 28-day Forward Plan, 5-day consideration and 3-day call in period have been approved.

 

The Cabinet Member authorised:

 

1.     Authorised the award of a contract to Pick Everard for the provision of Multi-Disciplinary Design Team (MDDT) Services over RIBA Stages 1-6 for the Vine in Central Library - at a total contract value of £495,995.51 for the period 22 April 2024 to 16 March 2027.

2.     Delegated authority to the Executive Director of Place and Economy to take all necessary steps to implement the decision in recommendation 1 including the entering into any of any necessary legal agreements.

 

Decision type: Key

Reason Key: Expenditure or savings greater than £500,000;

Decision status: Recommendations Approved

Wards affected: Central;

Notice of proposed decision first published: 08/05/2024

Decision due: 8 May 2024 by Cabinet Member for Housing, Growth and Regeneration

Lead member: Cabinet Member for Housing, Growth and Regeneration