Approval for contract to be awarded to Milestone to deliver construction of Eastern Industries Access Improvement Scheme - KEY/27FEB23/03

The Council is to receive funding from the Cambridgeshire and Peterborough Combined Authority (CPCA) to deliver construction of the Eastern Industries Access Improvement Scheme. The total amount to be funded is £6,665,696. Approval is required for contract to be awarded to Milestone to undertake delivery of the improvement scheme.

Decision type: Key

Reason Key: Expenditure or savings greater than £500,000;

Decision status: Recommendations Approved

Wards affected: East;

Notice of proposed decision first published: 27/01/2023

Decision due: 13 Mar 2023 by Cabinet

Lead member: Councillor Marco Cereste, Mayor of Peterborough marco.cereste@peterborough.gov.uk

Lead director: Executive Director Place and Economy

Department: Place and Economy

Contact: Lewis Banks, Transport & Environment Manager Email: lewis.banks@peterborough.gov.uk Tel: 01733 317465.

Consultation process

Consultation was undertaken with relevant stakeholders (councillors, residents, cycle forum, etc.) during design of the scheme.

Relevant Scrutiny Committee: Climate Change And Environment Scrutiny Committee

Decisions

Agenda items

Documents

  • Meeting minutes confirming award