To approve works to the Stanground bypass and
authorise the associated package of work to be issued to Skanska
Construction UK Limited under the Council’s existing
agreement with SKANSKA dated 18th September 2013 (the Highways
Services Agreement).
Decision type: Key
Reason Key: Expenditure or savings greater than £500,000;
Decision status: Abandoned
Wards affected: Hargate and Hempsted; Stanground South;
Notice of proposed decision first published: 02/08/2019
Decision due: March 2022 by Cabinet Member for Strategic Planning and Commercial Strategy and Investments
Lead member: Cabinet Member for Strategic Planning and Commercial Strategy and Investments
Lead director: Steve Cox
Department: Place and Economy
Contact: Charlotte Palmer Charlotte Palmer, Group Manager – Transport and Environment, Email: charlotte.palmer@peterborough.gov.uk Email: charlotte.palmer@peterborough.gov.uk Tel: 01733 453538.
Consultation process
Relevant internal and external
stakeholders
Standard consultation for highway schemes