Issue details

To approve additional Local Highways Maintenance funding - KEY/24DEC18/02

The Cabinet Member:

 

1.    Authorised the issue of the following work package to Skanska Construction UK Limited under the Council’s existing Peterborough Highway Services Contract;

 

·         Additional highway maintenance funding for 018/19 - KEY/24DEC02/18. Work package value is £1.535m.

 

2.    Authorised the Director of Growth and Regeneration to vary the work order value when required subject to;

 

                              I.        available budget being in place;

                            II.        the total sum of each variation not exceeding £100,000.

                           III.        the combined value of any authorised variation(s) do not exceed the total sum of £500,000. Any variations are to be made in prior consultation with internal audit, finance and legal services.

 

Decision type: Key

Reason Key: Expenditure or savings greater than £500,000;

Decision status: Recommendations Approved

Wards affected: (All Wards);

Notice of proposed decision first published: 23/11/2018

Decision due: Not before 15th Jan 2019 by Cabinet Member for Growth, Planning, Housing and Economic Development

Lead member: Cabinet Member for Growth, Planning, Housing and Economic Development

Lead director: Simon Machen

Department: Place and Economy

Contact: Martin Brooker Martin Brooker, Senior Engineer, 01733 452691, Email: martin.brooker@peterborough.gov.uk Email: Martin.Brooker@peterborough.gov.uk.

Consultation process

Relevant internal and external stakeholders.

Appropriate consultation will be undertaken on individual schemes as required.

Relevant Scrutiny Committee: Growth, Environment and Respirces Scrutiny Committee

Decisions

Documents