Issue details

Approval for contract to be awarded to Skanska to deliver widening of the A605 Oundle Road between Alwalton and Lynch Wood Business Park - KEY/11JUN18/03

The Cabinet Member:

 

1.    Authorised the issue of the following work package to Skanska Construction UK Limited under the Council’s existing Peterborough Highway Services Contract;

 

·         Recommendation to approve the A605 Oundle Road improvements programme KEY/11JUN18/03. The total budget is £2.293m.

·         Below is a breakdown of costs to date and future forecast .

 

Year

£

2017/18

67,795.62

2018/19

210,854.57

2019/20 Actual Apr19 to Oct19

92,535.30

2019/20 Forecast Nov19 to Mar20

1,121,814.13

2020/21 Budget

800,000.00

Total

2,292,999.62

 

Decision type: Key

Reason Key: Expenditure or savings greater than £500,000;

Decision status: Recommendations Approved

Wards affected: Orton Waterville;

Notice of proposed decision first published: 11/05/2018

Decision due: Not before 26th Nov 2019 by Cabinet Member for Strategic Planning and Commercial Strategy and Investments

Lead member: Councillor Peter Hiller, Cabinet Member for Housing, Growth and Regeneration peter.hiller@peterborough.gov.uk

Lead director: Executive Director Place and Economy

Department: Place and Economy

Contact: Lewis Banks, Transport & Environment Manager Tel: 01733 317465, Email:  lewis.banks@peterborough.gov.uk  lewis.banks@peterborough.gov.uk Tel: 01733 317465.