The Cabinet Member:
1. Authorised the issue of the following work package to Skanska Construction UK Limited under the Council’s existing Peterborough Highway Services Contract;
· Recommendation to approve the A605 Oundle Road improvements programme KEY/11JUN18/03. The total budget is £2.293m.
· Below is a breakdown of costs to date and future forecast .
Year |
£ |
2017/18 |
67,795.62 |
2018/19 |
210,854.57 |
2019/20 Actual Apr19 to Oct19 |
92,535.30 |
2019/20 Forecast Nov19 to Mar20 |
1,121,814.13 |
2020/21 Budget |
800,000.00 |
Total |
2,292,999.62 |
Decision type: Key
Reason Key: Expenditure or savings greater than £500,000;
Decision status: Recommendations Approved
Wards affected: Orton Waterville;
Notice of proposed decision first published: 11/05/2018
Decision due: Not before 26th Nov 2019 by Cabinet Member for Strategic Planning and Commercial Strategy and Investments
Lead member: Councillor Peter Hiller peter.hiller@peterborough.gov.uk
Lead director: Executive Director Place and Economy
Department: Place and Economy
Contact: Lewis Banks, Transport & Environment Manager Tel: 01733 317465, Email: lewis.banks@peterborough.gov.uk lewis.banks@peterborough.gov.uk Tel: 01733 317465.