Peterborough City Council

Home | On-Line Services | Site Map | Adv. Search | Help | Contact Us | News | Accessibility | Return to graphics mode
A-Z of Services | About Peterborough | Advice & benefits | Business | Community & living | Council & democracy | Education & learning | Environment & planning | Health & social care | Housing | Jobs and careers | Leisure & culture | Streets & transport
 
 
Calendar
Committees
Decisions
Forward plans
Library
Meetings
Outside Bodies
Parish Councils
Search documents
Statistics
Subscribe to updates
What's new
Your Councillors
Your MEPs
Your MPs
 

Issue details

A605 Whittlesey Access Phase 2 - Stanground Access - KEY/25DEC17/03

The Cabinet Member authorised the issue of a work package to undertake improvement works on the A605 Stanground east junction. The total value of the package will be £5m of which £2.8m has been awarded to the Council from the Department for Transport (DfT), via the Cambridgeshire and Peterborough Combined Authority, and £2.2m has been allocated as part of the Council’s MTFS.

 

Spend to date is £428k, below is a breakdown of spend to date and future forecast:

 

Year

 

£

2017/18

Actual

41,314.57

2018/19

Actual

226,499.24

2019/20

Actual YTD

160,249.39

2019/20

Forecast

3,071,936.37

2020/21

Budget

1,500,000.00

Total

 

4,999,999.57

 

 

The following governance processes have been undertaken:

 

·         Contract exemption report awarded to BT up to the value of £4119 signed off on 20 June 2018

·         Contract exemption report awarded to Cadent up to the value of £22172 signed off on 26 March 2018

·         Contract exemption report awarded to Vodafone up to the value of £4000 signed off on 20 June 2018

·         Contract exemption report awarded to Virgin Media up to the value of £20,407 signed off on 20 June 2018

 

Decision type: Key

Reason Key: Expenditure or savings greater than £500,000;

Decision status: Recommendations Approved

Wards affected: Stanground South;

Notice of proposed decision first published: 24/11/2017

Decision due: Not before 12th Dec 2019 by Cabinet Member for Strategic Planning and Commercial Strategy and Investments

Lead member: Councillor Peter Hiller, Cabinet Member for Strategic Planning and Commercial Strategy and Investments peter.hiller@peterborough.gov.uk

Lead director: Executive Director Place and Economy

Department: Place and Economy

Contact: Lewis Banks, Principal Transport Planning Officer Tel: 01733 317465, Email:  lewis.banks@peterborough.gov.uk  lewis.banks@peterborough.gov.uk Tel: 01733 317465.

Consultation process

Relevant internal and external stakeholders.

 

The scheme is included in the fourth Local Transport Plan. Further consultation will be undertaken during the design process, including ward Councillors.

Relevant Scrutiny Committee: Growth, Environment and Resources Scrutiny Committee

Decisions

Documents

 

 

 
Peterborough City Council. Town Hall, Bridge Street, Peterborough, PE1 1HF - (01733) 747474
 
Return to graphics mode