The Cabinet member:
1. Authorised the issue of the work package to Skanska Construction UK Limited under the Council’s existing Peterborough Highway Services Contract for Skanska to undertake works and services to deliver the Council’s TRANSPORT PROGRAMME OF PARKWAY MAINTENANCE – (KEY/01MAY17/03). The work package issued is for a value of £2.3m in 2017/18 and then a further £1.5m per year from 2018/19 to 2021/22 (£8.3 million in total). This will be funded through the medium term financial strategy.
2. Authorised the Director of Growth and Regeneration to vary the works order value when
required subject to;
i. available budget being in place;
ii. the total sum of each variation not exceeding £100,000,
iii. the combined value of any authorised variation(s) do not exceed the total sum of £500,000.
Any variations are to be made in prior consultation with internal audit, finance and legal services.
Decision type: Key
Reason Key: Expenditure or savings greater than £500,000;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 31/03/2017
Decision due: Not before 1st Aug 2017 by Cabinet Member for Growth, Planning, Housing and Economic Development
Lead member: Cabinet Member for Growth, Planning, Housing and Economic Development
Lead director: Executive Director Place and Economy
Department: Place and Economy
Contact: Lewis Banks, Transport & Environment Manager Email: lewis.banks@peterborough.gov.uk Email: lewis.banks@peterborough.gov.uk Tel: 01733 317465.
Relevant Scrutiny Committee: Growth, Environment and Resources Scrutiny Committee