Recommendation to approve the virement of £1.3 million from the Bourges Boulevard Phase 2 Improvements project to the Jct 20 Capacity Improvements project. This is in order to undertake additional works whilst on site to avoid future disruption to the network and as such maximise the use of available funding. Both projects are fully funded by the Local Enterprise Partnership (LEP)
Decision type: Key
Reason Key: Expenditure or savings greater than £500,000;
Decision status: Abandoned
Wards affected: Dogsthorpe; Gunthorpe; Paston and Walton;
Notice of proposed decision first published: 23/12/2016
Decision due: January 2017 by Cabinet Member for Growth, Planning, Housing and Economic Development
Lead member: Cabinet Member for Growth, Planning, Housing and Economic Development
Lead director: Executive Director Place and Economy
Department: Place and Economy
Contact: E-mail: Martin.Brooker@peterborough.gov.uk Tel: (01733) 45269.
Relevant Scrutiny Committee: Growth, Environment & Resources