The Cabinet Member:
1) Authorised the issue ofthe following work packages to Skanska Construction UK Limited under the Council’s existing Peterborough Highway Services Contract;
i. Junction 20 (Paston Parkway/A47) capacity improvements, work package value tobe within £5m scheme budget
ii. Bourges Boulevard Phase 2,work package value to be within scheme budget of £10.5m
iii. Wheel Yard public realm improvements, work package value tobe within scheme budget of £690k
iv. LED streetlighting upgrades, work package value tobe within scheme budget of £16.681m
v. A1260 Nene Parkway,work package value tobe within scheme budget of£1.5m
vi. A1179 Longthorpe Parkway,work package value to be within scheme budget of £1.5m
2) Authorised the Director ofGrowth and Regeneration to vary the work order value when required subject to;(i) available budget being in place; (ii) the total sum ofeach variation not exceeding £100,000, and (iii) the combined value ofany authorised variation(s) do not exceed the total sum of£500,000. Any variations are to be made in prior consultation with internal audit, finance and legal services.
Decision type: Key
Reason Key: Expenditure or savings greater than £500,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 11/12/2015
Decision due: Not before 5th Apr 2016 by Cabinet Member for Growth, Planning, Housing and Economic Development
Lead member: Councillor Peter Hiller peter.hiller@peterborough.gov.uk
Lead director: Executive Director Place and Economy
Department: Place and Economy
Contact: Amy Petrie, Principal Programme and Project Officer Email: amy.petrie@peterborough.gov.uk; Tel: 01733 452272 Email: amy.petrie@peterborough.gov.uk Tel: 01733 452272.
Consultation process
Relevant internal and external stakeholders.
Relevant Scrutiny Committee: Sustainable Growth and Environment Capital
Meeting Open to Public: n/a