Decisions

Decisions published

19/01/2022 - Interim Management of the Key Theatre - JAN22/CMDN/69 ref: 1918    Recommendations Approved

With the approval of the Chairman of the Communities Scrutiny Committee, the urgency procedure and special urgency procedure have been invoked to suspend the requirement to publish notice of the decision for the full 28 days and to suspend the requirement for a 5-day consideration period. The decision will still be subject to call-in. These procedures have been invoked as the Council has worked hard to identify a temporary operator for the Key Theatre, and Selladoor (the current operator of the New Theatre) are the only party immediately willing and able to fulfil this role. They are in a position, subject to successful lease negotiations, to take over from 1 February, meaning that all existing City Culture staff employed at the Key Theatre would subject to statutory consultation transfer under TUPE legislation resulting in no immediate redundancies, and pre-booked shows would be able to continue uninterrupted. The incumbent caterer Chalkboard Limited would become a sub-tenant of Selladoor. The arrangement with Selladoor will enable PCC to consider all options for the future of the premises and develop a viable business plan.

 

The Cabinet Member approved the award of a Lease to Selladoor Venue Development Ltd (operators of the New Theatre Peterborough) to operate the Key Theatre for a period of 5 years, with annual break clauses, from 1 February 2022. 

Decision Maker: Deputy Leader and Cabinet Member for Housing, Culture and Communities

Decision published: 19/01/2022

Effective from: 25/01/2022

Wards affected: (All Wards);

Lead officer: Adrian Chapman


14/01/2022 - Approval for contract to be awarded to Milestone to deliver the new traffic signals maintenance fund – JAN22/CMDN/68 ref: 1917    Recommendations Approved

The Cabinet Member:

 

 

1.    Approved the award of £500k to deliver a scheme to upgrade traffic signals at the Lincoln Road / Taverners Road signalised junction. Contract to be awarded to Milestone Infrastructure Limited to deliver the construction phase of the scheme as per the Peterborough Highway Services contract.

 

Decision Maker: Cabinet Member for Strategic Planning and Commercial Strategy and Investments

Decision published: 14/01/2022

Effective from: 20/01/2022

Wards affected: Central; North; Park;

Lead officer: Lewis Banks