Termination of contract with Eco-Modular Buildings - JUL23/CMDN/17

Decision Maker: Cabinet Member for Skills, Education and Children's Services'

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This report seeks the Cabinet Member’s approval to the recommendations to enable the design and build contract with Eco-Modular Buildings Ltd to be terminated.

Reasons for the decision:

·         To enable the Council to commission contractors to resolve the remaining snags and defects at the school site.

·         Remove the contractual relationship and utilise the retention monies to resolve remaining snags and defects at the site.

Alternative options considered:

Do nothing – This is not an option as termination will remove the contractual relationship and enable the Council to utilise the contract retention monies to resolve remaining snags and defects at the school site.

 

Interests and Nature of Interests Declared:

There were none.

Background Documents:

Publication date: 10/07/2023

Date of decision: 10/07/2023

Effective from: 14/07/2023